Bitdeer ($BTDR) will deploy approximately 28MW of Bitcoin (BTC) mining equipment at Soluna ($SLNH)'s wind-powered data center in Texas. The expected hash rate from the deployment is about 1.93 EH/s. Soluna announced on August 25 that it signed a contract with Bitdeer's subsidiary Dory Creek, with deployment set to begin in September.
The agreement combines Bitdeer's mining equipment with Soluna's power and operational infrastructure. The facility, Project Kati 1 in Wilshire County, Texas, is an 83MW wind-powered data center where the equipment will be deployed incrementally. The confirmed contract size is 28MW.
Bitdeer will supply and own its Sealminer A2 Pro Air ASIC miners, while Soluna provides land, power, and operational infrastructure. Both companies agreed to share mining revenue, differing from traditional hosting models that charge fixed fees. In this joint mining structure, Soluna receives a portion of the mining revenue instead of a fixed rental fee, with revenues subject to Bitcoin price, network difficulty, equipment efficiency, and facility uptime.
Soluna CEO John Belizaire stated, "Joint mining is a natural extension of our operational experience," adding that it allows them to directly participate in results generated by their infrastructure alongside partners.
Details on revenue sharing ratios, power costs, operating expenses, and contract duration were not disclosed. Bitdeer's official data states the Sealminer A2 Pro Air has a hash rate of 255-270 TH/s per unit with power efficiency around 14.9 J/TH. Actual hash rates may vary based on equipment quantity, installation schedule, power supply, and facility uptime.
Soluna reported total operational data center capacity at 192MW as of Q2, with Project Kati 1 operating at 48MW and 14MW under construction. The facility recorded positive net income of $820,000 (about 11 billion won) in Q2 for the first time.
This deployment marks Soluna's direct participation in mining revenue using its power infrastructure. While revenue volatility may be higher than fixed hosting fees, specific cost burdens and distribution structures remain undisclosed. Soluna is also advancing AI and high-performance computing (HPC) data center projects alongside mining, with a development pipeline of approximately 6.3GW that includes operational capacity as well as planned, developing, and evaluated projects.
SEC filings dated September 8 confirmed Project Kati 1's final 14MW was operational, with Bitdeer equipment being delivered and deployed per the August announcement. However, completion status and final operational capacity were not disclosed. The "additional 7MW" figure mentioned in sourcing materials was not verified by Soluna's official announcements or SEC filings.