IREN's Texas 2GW Data Center Hub Conditionally Included in ERCOT Grid Connection

The $2GW-scale Sweetwater data center hub in Texas is conditionally included in the power grid interconnection process. IREN announced on August 8 that the Sweetwater hub has been conditionally classified as a base load under ERCOT's 'Placement Zero' procedure.
The Sweetwater hub consists of Sweetwater 1 (1.4GW) and Sweetwater 2 (600MW). IREN stated that the high-voltage substation for Sweetwater 1 began supplying power earlier this year, with construction underway for a 300MW data center aiming to begin operations in Q4 2027.
ERCOT's Placement Zero procedure is a bulk review process for large-scale power demand connections exceeding 75MW. ERCOT operates under a system that classifies major power demands as base load, additional review required, or future procedure candidates.
Korean Source
This article is an English localization of a Korean-language crypto news report. Original headline: IREN, 텍사스 2GW 데이터센터 ERCOT에 조건부 포함